Contact

Case Study

Project Name: Allen Court
Location:Ridding Lane, Ealing UB6 0JZ
Client:Linden Homes
Duration: May 2016 - June 2016
Project Value: £105,000

We were appointed to erect a scaffold around the 11 storey Allen Court building. The scaffold was required so that the building could be progressively deconstructed. The building was within 15m of the Piccadilly Line. To comply with LU requirements the scaffold had to be Monarflexed on one elevation. the remaining 3 elevations were debris netted.

Scope:

Erect tubular fully boarded scaffold around the entire 11 storey building.

Entire scaffold was encapsulated with Monarflex on one elevation and debris netting on the remaining 3.

A debris fan was erected over an access road so that it could remain in use.

As the building was deconstructed handrails were installed around the lift shafts and staircases to protect the workers from the open edges.

The scaffold was progressively struck as the building was deconstructed.

Latest News

If you are planning to have any building or renovation work carried out in Essex on your building, you will want to...

By Matthew High

Scaffolding Project at Ilford Station During the lead-in period to Christmas Inner City Scaffolding and our sister company Downwell Demolition were busy. We...

By Matthew High

go to top

January COVID-19 Lockdown – Continuance of work

 

Following the Prime Ministers' announcement on Monday 4th January 2021 regarding the 3rd national lockdown,

Inner City Scaffolding will carry on business as usual.

 

Our strict COVID- 19 procedures and measures that we put in place in March will continue at all times

Our priority is to ensure the safety of our workforce, subcontractors, and the general public at all times.