Name: Mar House

Location: London

Sector: Residential

Solution: (Re)cladding Solutions

Value: £200,000

Scope

Inner City Scaffolding was appointed to provide phased access solutions to support cladding remediation works at Mar House. The project required a flexible scaffold strategy to accommodate three distinct stages of repair, including bridging over the main entrance and adapting to tight site constraints. 

Our team delivered a combination of standard and compact HAKI staircases, stacked loading bays for telehandler access, and full flame-retardant debris netting to ensure safety and compliance throughout the 20-week programme. 

Key Deliverables

  • Phased Scaffold Installation: 3 scaffold phases erected in 3m floor-level lifts to support staged cladding works
  • Entrance Bridging: Scaffold bridged over the main entrance to maintain access
  • Loading & Access: Stacked loading bays for telehandler efficiency; and 2nr HAKI staircases, including 1 compact HAKI for restricted elevation access
  • Safety Measures: Certified flame-retardant debris netting across all scaffold elevations 

Outcome

Mar House demonstrated Inner City Scaffolding’s ability to adapt scaffold design to evolving site needs and spatial constraints. Our phased approach and compact access solutions ensured minimal disruption and maximum efficiency across all stages of the cladding repair programme.