We were appointed to supply and erect a temporary roof over the top of the a large residential property in Finchley, North London. The property had suffered fire damage resulting in the roof needing to be replaced.

Scope of Works

  • Erect 6 fully boarded elevations at the front and the back of the property to allow the workers a safe working platform to replace the roof.
  • Extend the scaffold up past the existing damaged pitched roof leaving a meter of clearance.
  • Span across the front and back scaffolds with ladder beams.
  • Cover the ladder beams with corrugated steel sheeting. The corrugated sheets are overlapped by 150mm and then attached to the beam using wriggly clips.
  • Encapsulate the top 2 lifts of the scaffold with flame retardant Monarflex.
  • Install security system on the scaffold to detect intruders.

Project Name:
Fitzjohn Avenue

Location:
Finchley, North London

Client:
AEM Contractors

Duration:
6 Months

Project Value:
£26,000

  • Spacer
  • Spacer
  • Spacer
  • Spacer
  • Spacer
  • Spacer
  • Spacer
  • Spacer
  • Spacer
  • Spacer

CONTACT US TODAY TO DISCUSS HOW WE CAN ASSIST YOUR REQUIREMENTS

Contact

Please select the division you wish to connect with:

Please leave this field empty.

Newsletter