Middlesex St (Phase 1)

Project Name: Middlesex St (Phase 1)
Location:Middlesex St, London, E1 7TP
Client:Tolent Construction
Duration: April 2016 - August 2016
Project Value: £175,000

We were appointed to erect protection scaffolding around Cromlech House on Middlesex St so that it can safely be demolished. The project has been divided up into 2 phases with phase 2 coming later. The scaffolding was required on both the east and west elevations of the building to provide protection to the pedestrians and traffic moving down Middlesex St & Goulston St.

Scope of Works

Erect 5500m2 of scaffolding to provide protection so the 4 storey concrete framed structure can be demolished.

60m protection fan added to the Middlesex St elevation so that the pedestrians can safely move by the site

Encapsulate scaffold with flame retardant Monarflex

Latest News

Unlike Captain Mainwaring from the Classic British TV Comedy ‘Dads Army’ Inner City Scaffolding would be only too pleased to go top...

By Alan Knight

Inner City Scaffolding always reach new heights in Scaffolding Services and would like to go to the top of your suppliers list...

By Alan Knight

go to top